Rural bridge program completed

MoDot says the last of 31 bridges in a bundled replacement project opened in northern Missouri this month, marking the completion of the Fixing Access to Rural Missouri (FARM) Bridge Program. The program replaced 31 bridges across northern Missouri that were weight-restricted, supported by timber piles, in poor condition, and were one lane but carried two-way traffic. The replacements were funded by a $20.8 million Competitive Highway Bridge Program grant from the Federal Highway Administration in 2018, as well as $5.2 million from the Missouri Department of Transportation. When the Route T bridge over Fitzgerald Branch in Gentry County opened this month, it marked the program’s completion – one month ahead of schedule.