Randolph County road work begins March 24th

MoDot says Weather permitting, a resurfacing project located on Route DD in Randolph County, from U.S. Route 24 in Moberly to the end of state maintenance, is expected to begin March 24, 2025.
The $2.4M contract, awarded last year to Capital Paving & Construction, LLC of Columbia, Missouri, includes additional resurfacing projects in Randolph County that are scheduled to begin immediately following the completion of Route DD. All work is scheduled to be completed by mid-May.

Route D – from Route C near Huntsville to Route BB
Route BB – from Missouri Route 3 to Route A near Moberly
Traffic will be reduced to one lane with a 10-foot width restriction at the location where crews are actively working.